A little bit here...a little bit there.
The dining room floor has been stained! Which apparently means the lights, which are in, will be going in soon. The trim seems to have stalled, but we'll see.
The cable, phone, and electric lines are all in the ground. Now the excavator can close that trench up.
There is also a stockpile of ducting in the basement, so that appears to be ramping up.
The kitchen cabinets are scheduled to go in Sept. 26th, so Julie and I are heading to the Corian place to choose our countertop tomorrow morning.
Summary of stuff yet to be done:
- Kitchen Cabinets (Sept. 26)
- Carpet
- Plumbing Fixtures (After kitchen cabinets)
- Duct Work
- Heat Pump (after duct work)
- Water Heater (well is in)
- Final Grading